Bid and Codnstruction Scheule
|
Action Date
|
Task
|
|
Week of Sept. 25, 2006
|
Advertise for bids
|
|
Week of Nov. 6, 2006
|
Open construction bids
|
|
April 11, 2007
|
Award construction bid
|
|
May 8, 2007
|
Project Groundbreaking
|
|
May 2009
|
Project Completion
|
|
Construction Phasing
Mission Reach Segment 1:
Lone Star to San Pedro Creek: Mid 2007 through Mid 2009
Mission Reach Segment 2:
San Pedro Creek to San Juan Diversion: Mid 2008 through Mid 2010
Mission Reach Segment 3:
San Juan Diversion to Espada Dam: Early 2010 through Mid 2011
Mission Reach Segment 4:
Espada Dam to Mission Espada: Late 2010 through Mid 2012
|