Activity
|
Dates
|
|
SARA Board of Directors and San Antonio City Council adopt resolutions supporting a conceptual plan for San Antonio River from Guenther Street to Espada Dam.
|
March 1993
|
|
SARA Board of Directors and San Antonio City Council adopt resolutions supporting a conceptual plan for San Antonio River from Nueva Street to U.S. Highway 281
|
November/December 1993
|
|
SARA presents Bexar County with proposal to fund improvements to the San Antonio River
|
Spring 1996
|
|
SARA, Bexar County and City of San Antonio form Committee of Six comprised of elected representatives from each entity to serve as the oversight committee to guide the San Antonio River Improvements Project
|
Spring 1998
|
|
SARA and Bexar County conduct series of public meetings and community workshops on San Antonio River Improvement Project
|
August October 1998
|
|
Committee of Six forms San Antonio River Oversight Committee
|
Fall 1998
|
|
Bexar County Commissioners Court passed resolution stating financial commitment of up to $73 million of flood control improvements on San Antonio River Improvement Project
|
May 4, 1999
|
|
Congress passes the Water Resources Development Act of 2000 authorizing the U.S. Army Corps of Engineers (USACE) to expand the purposes of the previously authorized San Antonio Channel Improvement Project to include ecosystem restoration and recreation
|
November 2000
|
|
Complete Final Design on Downtown Reach
|
December 2000
|
|
Initiate construction on Downtown Reach
|
Jan. 2001
|
|
City of San Antonio sets funding commitment to San Antonio River Improvements Project at $37.8 million based upon Concept Design estimate
|
April 2001
|
|
Complete Construction of Downtown Reach (Downtown project completed three months early and $500,000 under budget)
|
October 2002
|
|
Completion of Preliminary Design: Museum Reach
|
October 2003
|
|
USACE releases National Environmental Restoration Plan announcing federal “interest” in the Mission Reach only and setting federal funding level in the project
|
April 2004
|
|
City, County, SARA staff decision to recommend Scenario “G” with private funded components (if funds were available). Scenario “G” with private funding proposed the following schedule:
- Final Drawings September 2006.
-
Bidding finished by November 2006.
-
Construction started December 2006.
-
Completed by Dec. 2010
Scenario G includes full design of public and privately funded project components and construction documents for public components and bid alternates for amenities as funds become available from other sources.
|
July/August 2004
|
|
Committee of Six authorizes Final Design, including Scenario G on the Museum Reach: Urban Segment
|
August 2004
|
|
City and County Authorize Final Design Phase for Mission Reach and Museum Reach. City approves MOU with SARA
|
September 2004
|
|
Congress appropriates $1,625,000 for FY 2005 to support USACE design phase
|
November 2004
|
|
Congress appropriates $2,730,000 for FY 2006 to support USACE design phase
|
November 2005
|
|
City, County and SARA begin working on Interlocal Agreement to outline roles and responsibilities on the implementation of project, specifically addressing the accelerated segment of the Museum Reach
|
January 2006
|
|
U.S. House approves $2.35 million for FY 2007 to support USACE design and construction
|
May 24, 2006
|
|
Ford Powell and Carson submits 50% final design documents
|
June 5, 2006
|
|
U.S. Senate approves $10 million for FY 2007 to support USACE design and construction
|
June 29, 2006
|
|
Committee of Six approves revised budget for Museum Reach of $49.9 million
|
August 11, 2006
|
|
USACE hosts 30% design review meeting on Mission Reach
|
August 16 18, 2006
|
|
Ford, Powell, and Carson submits 90% final design documents
|
August 21, 2006
|
|
SARA and USACE execute Project Cooperation Agreement for Mission Reach project signaling the beginning of the construction phase of the project with the USACE
|
August 24, 2006
|
|
USACE authorized design for 60% of Phase I of Mission Reach
|
August 29, 2006
|
|
Assistant Secretary of the Army John Paul Woodley visits San AntonioóPress Conference on Mission Reach Project with Judge Wolff and Commissioner Rodriguez
|
September 7, 2006
|
|
Bexar County approves $5.3 million in addition funding for Museum Reach Urban Segment
|
September 12, 2006
|
|
City Council contracts with PBS&J to perform project management services on river project
|
September 14, 2006
|
|
SARA hosts two public meetings on the 30% design on the Mission Reach
|
September 18-19, 2006
|
|
City Council is presented staff plan to fund $19 million in additional funding the Museum Reach Urban Segmentóincluding funding for amenities
|
September 20, 2006
|
|
Silver Ventures donates $3 million to Museum Reach Urban Segment
|
September 1, 2006
|
|
Committee of Six presented 90% Cost Estimate on Museum Reach Urban segment and presented 30% design status on Mission Reach
|
|
|
SARA initiates bid process for Museum Reach-Urban Segment
|
October 5, 2006
|
|
City of San Antonio approves Interlocal Agreement with County and SARA for SA River Project including additional funding for the amenities on the Urban Segment of the Museum Reach
|
October 12, 2006
|
|
SARA approves Interlocal Agreement with County and City for the SA River Project and agreement with County for project financing
|
October 18, 2006
|
|
Bexar County Commissioners Court approves Interlocal Agreement with the City and SARA for the SA River Project and approved agreement with SARA for Bexar County to finance the projectís construction
|
October 24, 2006
|
|
SARA secures USACE 404 Permit for Museum Reach Urban Segment
|
October 30, 2006
|
|
SARA received 100% estimate on Museum Reach Urban Segment
|
December 21, 2006
|
|
Bid opening for Museum Reach Urban Segment
|
January 19, 2007
|
|
AT&T announces $5 million donation to SA River Improvements Project
|
January 23, 2007
|
|
SARA secures TCEQ permit for Lock and Dam
|
January 26, 2007
|
|
USACE holds staff workshop to review 60% design of Phase I of Mission Reach
|
January 30-31, 2007
|
|
Joint Resolution of Congress passed to include funding to complete construction documents for the phase I of the Mission Reach
|
February 16, 2007
|
|
SARA awards Museum Reach Urban Segment construction contract to Zachry Construction Corporation
|
April 11, 2007
|
|
Groundbreaking ceremony held for Museum Reach Urban Segment
|
May 8, 2007
|
|
U.S. Senate approves $10 million for FY 2008 to support USACE design and construction
|
June 28, 2007
|
|
U.S. House approves $2 million for FY 2008 to support USACE design and construction
|
July 12, 2007
|